| Assessment Year | 2009 |
|---|---|
| Principal Product | Analytical Instruments |
| NAICS | 334516: Analytical Laboratory Instrument Manufacturing |
| SIC | 3826: Laboratory Analytical Instruments |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
130,000
ft2
|
| Annual Production | 17,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $56,972 | 1,304,000 |
kWh
|
$0.044 |
| Electricity Demand | $54,260 | 3,316 |
kW-mo/yr
|
$16.36 |
| Electricity Fees | $371 | - |
|
- |
| Natural Gas | $45,995 | 5,658 |
MMBtu
|
$8.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,820 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,370 | $3,610 |
$800
21,300
kWh
|
$570
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,440 | $26,850 |
$6,680
178,200
kWh
|
$8,740
-
kW-mo/yr
|
- | $40 | $(-20.0) | |
| 03 | 2.9114: Use solar heat to make electricty | $1,750 | $10,500 |
$550
14,600
kWh
|
$1,200
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.9112: Use solar heat to heat water | $1,750 | $11,200 | - | - |
$1,750
-
MMBtu
|
- | - | |
| 05 | 2.7243: Improve air circulation with destratification fans / other methods | $510 | $5,340 |
$(-140.0)
(-3,700)
kWh
|
$(-100.0)
-
kW-mo/yr
|
$750
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $20,820 | $57,500 |
$7,890
210,400
kWh
|
$10,410
-
kW-mo/yr
|
$2,500
-
MMBtu
|
$40 | $(-20.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs