ITAC Assessment: CO0624
ITAC logo
ITAC Assessment: CO0624
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Analytical Instruments
NAICS 334516: Analytical Laboratory Instrument Manufacturing
SIC 3826: Laboratory Analytical Instruments
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 130,000
ft2
Annual Production 17,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $56,972 1,304,000
kWh
Electricity Demand $54,260 3,316
kW-mo/yr
Electricity Fees $371 -
Natural Gas $45,995 5,658
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,820 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $1,370 $3,610 $800
21,300
kWh
$570
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $15,440 $26,850 $6,680
178,200
kWh
$8,740
-
kW-mo/yr
- $40 $(-20.0)
03 2.9114: Use solar heat to make electricty $1,750 $10,500 $550
14,600
kWh
$1,200
-
kW-mo/yr
- - -
04 2.9112: Use solar heat to heat water $1,750 $11,200 - - $1,750
-
MMBtu
- -
05 2.7243: Improve air circulation with destratification fans / other methods $510 $5,340 $(-140.0)
(-3,700)
kWh
$(-100.0)
-
kW-mo/yr
$750
-
MMBtu
- -
TOTAL RECOMMENDED $20,820 $57,500 $7,890
210,400
kWh
$10,410
-
kW-mo/yr
$2,500
-
MMBtu
$40 $(-20.0)
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs