ITAC Assessment: OR0325
ITAC logo
ITAC Assessment: OR0325
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Laminated Panels
NAICS
n/a
SIC 2435: Hardwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 140,000
ft2
Annual Production 72,700,000
thousand feet
Production Hrs. Annual 0
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $157,253 4,625,147
kWh
Electricity Demand $27,309 8,534
kW-mo/yr
Electricity Fees $6,636 -
Natural Gas $152,665 43,049
MMBtu
LPG $29,543 4,304
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,558 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,674

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.1133: Adjust burners for efficient operation $5,486 $500 - - $5,486
-
MMBtu
-
02 2.1243: Use heat from boiler blowdown to preheat boiler feed water $16,215 $6,816 - - $16,215
-
MMBtu
-
03 2.1133: Adjust burners for efficient operation $4,674 - - - $4,674
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,213 $1,000 $2,000
58,910
kWh
$213
-
kW-mo/yr
- -
05 3.5313: Increase amount of waste recovered for resale $970 - - - - $970
-
lb
TOTAL RECOMMENDED $29,558 $8,316 $2,000
58,910
kWh
$213
-
kW-mo/yr
$26,375
-
MMBtu
$970
-
lb
TOTAL IMPLEMENTED $4,674 - - - $4,674
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs