| Assessment Year | 1998 |
|---|---|
| Principal Product | Mechanical Packages |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $10 M to 50M |
| # of Employees | 40 |
| Plant Area |
72,000
ft2
|
| Annual Production | 52
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,442 | 1,366,354 |
kWh
|
$0.050 |
| Electricity Demand | $14,430 | 4,991 |
kW-mo/yr
|
$2.89 |
| Electricity Fees | $16,976 | - |
|
- |
| Natural Gas | $12,305 | 1,668 |
MMBtu
|
$7.38 |
| Fuel Oil #2 | $3,600 | 147 |
MMBtu
|
$24.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,846 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,021 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $9,292 | $3,361 | - | - | - |
$9,292
-
MMBtu
|
- | - | - | - | |
| 02 | 2.7261: Install timers and/or thermostats | $463 | $710 |
$428
9,086
kWh
|
- | $35 | - | - | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,444 | $892 |
$2,260
47,479
kWh
|
- | $184 | - | - | - | - | - | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,750 | - | - |
$9,414
-
kW-mo/yr
|
- | - | - | - | - | $(-1,664.0) | |
| 05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,460 | $954 |
$1,350
28,429
kWh
|
- | $110 | - | - | - | - | - | |
| 06 | 2.4314: Use synthetic lubricant | $577 | $308 |
$375
7,913
kWh
|
$118
-
kW-mo/yr
|
$84 | - | - | - | - | - | |
| 07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $15,435 | $2,360 | - | - | - | - | - |
$13,860
-
gal
|
$1,575
-
gal
|
- | |
| 08 | 3.6124: Burn waste oil for heat | $1,919 | $2,862 | - | - | - |
$1,919
-
MMBtu
|
- | - | - | - | |
| 09 | 4.652: Replace existing equipment with more suitable substitutes | $1,506 | $4,518 |
$(-2,229.0)
(-43,083)
kWh
|
- | - | - |
$3,600
-
MMBtu
|
- | - | $135 | |
| TOTAL RECOMMENDED | $40,846 | $15,965 |
$2,184
49,824
kWh
|
$9,532
-
kW-mo/yr
|
$413 |
$11,211
-
MMBtu
|
$3,600
-
MMBtu
|
$13,860
-
gal
|
$1,575
-
gal
|
$(-1,529.0) | ||
| TOTAL IMPLEMENTED | $3,021 | $1,200 |
$2,635
55,392
kWh
|
$118
-
kW-mo/yr
|
$268 | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs