ITAC Assessment: MS0114
ITAC logo
ITAC Assessment: MS0114
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Mechanical Packages
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area 72,000
ft2
Annual Production 52
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,442 1,366,354
kWh
Electricity Demand $14,430 4,991
kW-mo/yr
Electricity Fees $16,976 -
Natural Gas $12,305 1,668
MMBtu
Fuel Oil #2 $3,600 147
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,846 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,021

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #2 Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings
01 2.2437: Recover waste heat from equipment $9,292 $3,361 - - - $9,292
-
MMBtu
- - - -
02 2.7261: Install timers and/or thermostats $463 $710 $428
9,086
kWh
- $35 - - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,444 $892 $2,260
47,479
kWh
- $184 - - - - -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $7,750 - - $9,414
-
kW-mo/yr
- - - - - $(-1,664.0)
05 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,460 $954 $1,350
28,429
kWh
- $110 - - - - -
06 2.4314: Use synthetic lubricant $577 $308 $375
7,913
kWh
$118
-
kW-mo/yr
$84 - - - - -
07 3.2123: Convert to high volume low pressure (hvlp) paint guns $15,435 $2,360 - - - - - $13,860
-
gal
$1,575
-
gal
-
08 3.6124: Burn waste oil for heat $1,919 $2,862 - - - $1,919
-
MMBtu
- - - -
09 4.652: Replace existing equipment with more suitable substitutes $1,506 $4,518 $(-2,229.0)
(-43,083)
kWh
- - - $3,600
-
MMBtu
- - $135
TOTAL RECOMMENDED $40,846 $15,965 $2,184
49,824
kWh
$9,532
-
kW-mo/yr
$413 $11,211
-
MMBtu
$3,600
-
MMBtu
$13,860
-
gal
$1,575
-
gal
$(-1,529.0)
TOTAL IMPLEMENTED $3,021 $1,200 $2,635
55,392
kWh
$118
-
kW-mo/yr
$268 - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #2 Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs