ITAC Assessment: MS0112
ITAC logo
ITAC Assessment: MS0112
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Foam and Matresses
NAICS
n/a
SIC 3086: Plastics Foam Products
Sales Range $10
M
to 50
M
# of Employees 193
Plant Area 309,539
ft2
Annual Production 155,000
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,562 1,728,312
kWh
Electricity Demand $60,484 6,784
kW-mo/yr
Electricity Fees $8,234 -
Natural Gas $43,851 12,607
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,465 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,237

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.3137: Use power during off-peak periods $13,468 - - $13,269
-
kW-mo/yr
$199 - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,687 $30,818 $3,799
114,889
kWh
$3,774
-
kW-mo/yr
$114 - - -
03 2.7261: Install timers and/or thermostats $541 $994 $533
16,120
kWh
- $8 - - -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $8,006 - - - - $3,631
-
lb
- $4,375
05 4.322: Eliminate old stock and modify inventory control $7,763 $4,590 - - - - $7,763 -
TOTAL RECOMMENDED $37,465 $36,402 $4,332
131,009
kWh
$17,043
-
kW-mo/yr
$321 $3,631
-
lb
$7,763 $4,375
TOTAL IMPLEMENTED $29,237 $4,590 - $13,269
-
kW-mo/yr
$199 $3,631
-
lb
$7,763 $4,375
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs