Assessment Year | 1998 |
---|---|
Principal Product | Beverages |
NAICS |
n/a
|
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 48 |
Plant Area |
86,700
ft2
|
Annual Production | 2,200,000
pieces
|
Production Hrs. Annual | 4,400
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $72,182 | 1,686,694 |
kWh
|
$0.043 |
Electricity Demand | $47,216 | 6,557 |
kW-mo/yr
|
$7.20 |
Electricity Fees | $3,188 | - |
|
- |
Natural Gas | $32,552 | 6,208 |
MMBtu
|
$5.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,714 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $23,520 | $9,000 | n/a | - | - | $23,520 | - | - | - | - |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,198 | $8,073 | n/a |
$1,013
30,481
kWh
|
$1,153
-
kW-mo/yr
|
$32 | - | - | - | - |
03 | 2.2437: Recover waste heat from equipment | $3,589 | $2,068 | n/a | - | - | - |
$3,589
-
MMBtu
|
- | - | - |
04 | 2.4221: Install compressor air intakes in coolest locations | $149 | $103 | n/a |
$80
2,345
kWh
|
$67
-
kW-mo/yr
|
$2 | - | - | - | - |
05 | 2.2447: Heat water with exhaust heat | $3,658 | $10,841 | n/a | - | - | - |
$3,658
-
MMBtu
|
- | - | - |
06 | 2.7261: Install timers and/or thermostats | $525 | $1,160 | n/a |
$517
15,533
kWh
|
- | $8 | - | - | - | - |
07 | 2.8114: Change rate schedules or other changes in utility service | $109 | $27 | n/a | - | - | $109 | - | - | - | - |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $18,800 | - | n/a | - | - | - | - | - | - | $18,800 |
09 | 4.821: Pay bills on time to avoid late fees | $3,485 | $50 | n/a | - | - | - | - | - | $3,485 | - |
10 | 4.522: Modify storage space to avoid rental of a warehouse | $35,681 | $63,600 | n/a | - | - | - | - | $3,699 | $27,822 | $4,160 |
TOTAL RECOMMENDED | $91,714 | $94,922 |
$1,610
48,359
kWh
|
$1,220
-
kW-mo/yr
|
$23,671 |
$7,247
-
MMBtu
|
$3,699 | $31,307 | $22,960 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs