ITAC Assessment: MS0111
ITAC logo
ITAC Assessment: MS0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Beverages
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 48
Plant Area 86,700
ft2
Annual Production 2,200,000
pieces
Production Hrs. Annual 4,400
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,182 1,686,694
kWh
Electricity Demand $47,216 6,557
kW-mo/yr
Electricity Fees $3,188 -
Natural Gas $32,552 6,208
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,714 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $23,520 $9,000 n/a - - $23,520 - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,198 $8,073 n/a $1,013
30,481
kWh
$1,153
-
kW-mo/yr
$32 - - - -
03 2.2437: Recover waste heat from equipment $3,589 $2,068 n/a - - - $3,589
-
MMBtu
- - -
04 2.4221: Install compressor air intakes in coolest locations $149 $103 n/a $80
2,345
kWh
$67
-
kW-mo/yr
$2 - - - -
05 2.2447: Heat water with exhaust heat $3,658 $10,841 n/a - - - $3,658
-
MMBtu
- - -
06 2.7261: Install timers and/or thermostats $525 $1,160 n/a $517
15,533
kWh
- $8 - - - -
07 2.8114: Change rate schedules or other changes in utility service $109 $27 n/a - - $109 - - - -
08 3.5315: Lease / purchase baler; sell cardboard to recycler $18,800 - n/a - - - - - - $18,800
09 4.821: Pay bills on time to avoid late fees $3,485 $50 n/a - - - - - $3,485 -
10 4.522: Modify storage space to avoid rental of a warehouse $35,681 $63,600 n/a - - - - $3,699 $27,822 $4,160
TOTAL RECOMMENDED $91,714 $94,922 $1,610
48,359
kWh
$1,220
-
kW-mo/yr
$23,671 $7,247
-
MMBtu
$3,699 $31,307 $22,960
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs