Assessment Year | 1996 |
---|---|
Principal Product | Filters and Filtration Systems |
NAICS |
n/a
|
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 325 |
Plant Area |
206,000
ft2
|
Annual Production | 1,768,750
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $134,681 | 4,072,685 |
kWh
|
$0.033 |
Electricity Demand | $73,878 | 9,024 |
kW-mo/yr
|
$8.19 |
Electricity Fees | $5,862 | - |
|
- |
Natural Gas | $73,116 | 12,695 |
MMBtu
|
$5.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,737 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,693 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3132: Recharge batteries on during off-peak demand periods | $1,280 | - | - |
$1,280
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,839 | $7,200 |
$1,462
46,014
kWh
|
$1,377
-
kW-mo/yr
|
- | - | - | |
03 | 2.1113: Reduce combustion air flow to optimum | $6,251 | $1,000 | - | - |
$6,251
-
MMBtu
|
- | - | |
04 | 2.7261: Install timers and/or thermostats | $954 | $711 |
$954
30,188
kWh
|
- | - | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $12,000 | $6,500 | - | - | - | - | $12,000 | |
06 | 3.5316: Contract a wood pallet recycling company | $1,413 | - | - | - | - |
$1,413
-
lb
|
- | |
TOTAL RECOMMENDED | $24,737 | $15,411 |
$2,416
76,202
kWh
|
$2,657
-
kW-mo/yr
|
$6,251
-
MMBtu
|
$1,413
-
lb
|
$12,000 | ||
TOTAL IMPLEMENTED | $2,693 | - | - |
$1,280
-
kW-mo/yr
|
- |
$1,413
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs