Assessment Year | 1996 |
---|---|
Principal Product | wiring harnesses |
NAICS |
n/a
|
SIC | 3694: Electrical Equipment for Internal Combustion Engines |
Sales Range | $50 M to 100M |
# of Employees | 530 |
Plant Area |
55,000
ft2
|
Annual Production | 360,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $80,204 | 2,209,848 |
kWh
|
$0.036 |
Electricity Demand | $45,794 | 5,359 |
kW-mo/yr
|
$8.55 |
Electricity Fees | $2,317 | - |
|
- |
LPG | $1,432 | 267 |
MMBtu
|
$5.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $441,160 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,659 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,933 | $6,695 |
$2,379
78,546
kWh
|
$2,554
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7261: Install timers and/or thermostats | $1,936 | $5,000 |
$1,936
63,892
kWh
|
- | - | - | - | - | |
03 | 2.7261: Install timers and/or thermostats | $790 | $570 |
$790
26,084
kWh
|
- | - | - | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,838 | $80 |
$924
30,481
kWh
|
$914
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7227: Use water on air conditioning exchanger to improve heat transfer and increase air conditioner efficiency | $2,389 | $5,280 |
$1,519
50,117
kWh
|
$870
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.3212: Optimize plant power factor | $1,144 | $900 | - | - | $1,144 | - | - | - | |
07 | 3.1191: Change procedures / equipment / operating conditions | $428,130 | $50,000 | - | - | - |
$(-30,870.0)
-
lb
|
$(-45,000.0) | $504,000 | |
TOTAL RECOMMENDED | $441,160 | $68,525 |
$7,548
249,120
kWh
|
$4,338
-
kW-mo/yr
|
$1,144 |
$(-30,870.0)
-
lb
|
$(-45,000.0) | $504,000 | ||
TOTAL IMPLEMENTED | $7,659 | $12,265 |
$5,105
168,522
kWh
|
$2,554
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs