| Assessment Year | 1996 |
|---|---|
| Principal Product | Aluminum Die Castings |
| NAICS |
n/a
|
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $10 M to 50M |
| # of Employees | 164 |
| Plant Area |
93,000
ft2
|
| Annual Production | 32,000,000
pieces
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $210,058 | 10,901,524 |
kWh
|
$0.019 |
| Electricity Demand | $156,976 | 28,909 |
kW-mo/yr
|
$5.43 |
| Electricity Fees | $183,347 | - |
|
- |
| Natural Gas | $421,181 | 174,793 |
MMBtu
|
$2.41 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $94,888 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $645 | $1,502 |
$394
23,447
kWh
|
$251 | - | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $632 | $110 |
$386
23,154
kWh
|
$246 | - | - | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $73,061 | $33,000 | - | - |
$73,061
-
MMBtu
|
- | |
| 04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $20,040 | $31,500 | - | - | - |
$20,040
-
lb
|
|
| 05 | 3.5216: Recycle nonferrous dust | $510 | - | - | - | - |
$510
-
lb
|
|
| TOTAL RECOMMENDED | $94,888 | $66,112 |
$780
46,601
kWh
|
$497 |
$73,061
-
MMBtu
|
$20,550
-
lb
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs