| Assessment Year | 1996 |
|---|---|
| Principal Product | Airbag Ignitors |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $50 M to 100M |
| # of Employees | 70 |
| Plant Area |
150,000
ft2
|
| Annual Production | 13,000,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $236,871 | 4,337,632 |
kWh
|
$0.055 |
| Electricity Demand | $17,111 | 8,053 |
kW-mo/yr
|
$2.12 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,957 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,220 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7232: Replace existing hvac unit with high efficiency model | $723 | $3,150 |
$616
12,309
kWh
|
$107
-
kW-mo/yr
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $617 | $1,440 |
$617
12,309
kWh
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,975 | - |
$2,975
58,910
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,488 | $340 |
$5,855
116,061
kWh
|
$633
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $642 | $1,548 |
$598
11,723
kWh
|
$44
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $1,503 | $450 |
$1,503
29,894
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,389 | $23,683 |
$12,159
240,621
kWh
|
$1,230
-
kW-mo/yr
|
- | |
| 08 | 3.5213: Reuse scrap printed paper for make-ready | $1,620 | - | - | - |
$1,620
-
lb
|
|
| TOTAL RECOMMENDED | $27,957 | $30,611 |
$24,323
481,827
kWh
|
$2,014
-
kW-mo/yr
|
$1,620
-
lb
|
||
| TOTAL IMPLEMENTED | $22,220 | $27,173 |
$18,630
368,991
kWh
|
$1,970
-
kW-mo/yr
|
$1,620
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs