Assessment Year | 1995 |
---|---|
Principal Product | Electroplated Metal Components |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 21 |
Plant Area |
37,000
ft2
|
Annual Production | 1,200,000
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,960 | 889,215 |
kWh
|
$0.070 |
Natural Gas | $2,209 | 510 |
MMBtu
|
$4.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,687 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $1,444 | $3,310 | - |
$1,444
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $783 | $1,219 |
$783
10,258
kWh
|
- | |
03 | 2.2514: Cover open tanks | $627 | $666 |
$627
19,637
kWh
|
- | |
04 | 2.6218: Turn off equipment when not in use | $2,512 | $440 |
$2,512
78,253
kWh
|
- | |
05 | 2.4314: Use synthetic lubricant | $225 | $20 |
$225
2,931
kWh
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $96 | $100 |
$96
1,172
kWh
|
- | |
TOTAL RECOMMENDED | $5,687 | $5,755 |
$4,243
112,251
kWh
|
$1,444
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs