ITAC Assessment: MS0012
ITAC logo
ITAC Assessment: MS0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Bricks
NAICS
n/a
SIC 3251: Brick and Structural Clay Tile
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area
n/a
Annual Production 52,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $215,526 3,623,095
kWh
Natural Gas $427,606 139,828
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,219 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $2,294 $2,130 $2,294
-
kWh
-
02 2.4133: Use most efficient type of electric motors $5,208 $9,920 $5,208
117,233
kWh
-
03 2.4133: Use most efficient type of electric motors $342 $700 $342
7,034
kWh
-
04 2.2414: Use waste heat from hot flue gases to preheat $29,988 $15,000 - $29,988
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $387 $200 $387
8,206
kWh
-
TOTAL RECOMMENDED $38,219 $27,950 $8,231
132,473
kWh
$29,988
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs