ITAC Assessment: MS0005
ITAC logo
ITAC Assessment: MS0005
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Furniture
NAICS
n/a
SIC 2512: Wood Household Furniture, Upholstered
Sales Range $10
M
to 50
M
# of Employees 387
Plant Area 265,000
ft2
Annual Production 109,472
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $101,803 1,796,307
kWh
Natural Gas $24,437 3,913
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,010 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6231: Utilize controls to operate equipment only when needed $5,137 $2,700 $5,137
171,161
kWh
-
02 2.7227: Use water on air conditioning exchanger to improve heat transfer and increase air conditioner efficiency $1,737 $8,100 $1,737
58,030
kWh
-
03 2.2711: Utilize outside air instead of conditioned air for drying $628 $500 - $628
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,714 $1,321 $3,714
42,790
kWh
-
05 2.2437: Recover waste heat from equipment $1,794 $1,000 - $1,794
-
MMBtu
TOTAL RECOMMENDED $13,010 $13,621 $10,588
271,981
kWh
$2,422
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs