Assessment Year | 2000 |
---|---|
Principal Product | Recreation Equipment |
NAICS |
n/a
|
SIC | 3949: Sporting and Athletic Goods, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 405 |
Plant Area |
160,000
ft2
|
Annual Production | 8,700
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $162,822 | 4,348,769 |
kWh
|
$0.037 |
Electricity Demand | $50,350 | 860 |
kW-mo/yr
|
$58.55 |
Electricity Fees | $25,774 | - |
|
- |
Natural Gas | $168,823 | 48,015 |
MMBtu
|
$3.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,854 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $4,781 | $5,125 |
$3,727
85,873
kWh
|
$1,054
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $600 | $40 |
$483
11,137
kWh
|
$117
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,341 | $105 |
$1,107
25,498
kWh
|
$234
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $804 | $885 |
$(-572.0)
(-13,189)
kWh
|
$293
-
kW-mo/yr
|
$1,083
-
MMBtu
|
- | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,800 | - | - | - | - |
$1,800
-
lb
|
- | - | |
06 | 4.611: Begin a practice of predictive / preventative maintenance | $13,480 | $3,700 | - | - | - | - | $13,480 | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $33,048 | $2,000 | - | - | - | - | - | $33,048 | |
TOTAL RECOMMENDED | $55,854 | $11,855 |
$4,745
109,319
kWh
|
$1,698
-
kW-mo/yr
|
$1,083
-
MMBtu
|
$1,800
-
lb
|
$13,480 | $33,048 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs