Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Metal Stamping & Fabricating
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 82
Plant Area 80,000
ft2
Annual Production 19,917,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,250 1,290,739
kWh
Electricity Demand $15,243 385
kW-mo/yr
Electricity Fees $5,820 -
LPG $14,226 3,389
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,984 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,479

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $2,671 $3,945 $2,196
39,859
kWh
$475
-
kW-mo/yr
- - - -
02 2.4221: Install compressor air intakes in coolest locations $1,521 $118 $1,244
22,567
kWh
$277
-
kW-mo/yr
- - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,722 $40 $1,405
25,498
kWh
$317
-
kW-mo/yr
- - - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $515 - $436
7,913
kWh
$79
-
kW-mo/yr
- - - -
05 4.652: Replace existing equipment with more suitable substitutes $7,535 $7,500 - - $7,535
-
MMBtu
- - -
06 3.5316: Contract a wood pallet recycling company $1,040 - - - - - $1,040
-
lb
-
07 3.6124: Burn waste oil for heat $3,970 $3,500 - - - $3,970
-
gal
- -
08 4.445: Install equipment to move product $3,650 $1,300 - - - - - $3,650
09 2.4156: Establish a preventative maintenance program $5,360 $3,700 - - - - - $5,360
TOTAL RECOMMENDED $27,984 $20,103 $5,281
95,837
kWh
$1,148
-
kW-mo/yr
$7,535
-
MMBtu
$3,970
-
gal
$1,040
-
lb
$9,010
TOTAL IMPLEMENTED $16,479 $9,103 $5,281
95,837
kWh
$1,148
-
kW-mo/yr
- - $1,040
-
lb
$9,010
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs