Assessment Year | 2000 |
---|---|
Principal Product | Metal Stamping & Fabricating |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 82 |
Plant Area |
80,000
ft2
|
Annual Production | 19,917,000
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $65,250 | 1,290,739 |
kWh
|
$0.051 |
Electricity Demand | $15,243 | 385 |
kW-mo/yr
|
$39.59 |
Electricity Fees | $5,820 | - |
|
- |
LPG | $14,226 | 3,389 |
MMBtu
|
$4.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,984 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,479 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,671 | $3,945 |
$2,196
39,859
kWh
|
$475
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,521 | $118 |
$1,244
22,567
kWh
|
$277
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,722 | $40 |
$1,405
25,498
kWh
|
$317
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $515 | - |
$436
7,913
kWh
|
$79
-
kW-mo/yr
|
- | - | - | - | |
05 | 4.652: Replace existing equipment with more suitable substitutes | $7,535 | $7,500 | - | - |
$7,535
-
MMBtu
|
- | - | - | |
06 | 3.5316: Contract a wood pallet recycling company | $1,040 | - | - | - | - | - |
$1,040
-
lb
|
- | |
07 | 3.6124: Burn waste oil for heat | $3,970 | $3,500 | - | - | - |
$3,970
-
gal
|
- | - | |
08 | 4.445: Install equipment to move product | $3,650 | $1,300 | - | - | - | - | - | $3,650 | |
09 | 2.4156: Establish a preventative maintenance program | $5,360 | $3,700 | - | - | - | - | - | $5,360 | |
TOTAL RECOMMENDED | $27,984 | $20,103 |
$5,281
95,837
kWh
|
$1,148
-
kW-mo/yr
|
$7,535
-
MMBtu
|
$3,970
-
gal
|
$1,040
-
lb
|
$9,010 | ||
TOTAL IMPLEMENTED | $16,479 | $9,103 |
$5,281
95,837
kWh
|
$1,148
-
kW-mo/yr
|
- | - |
$1,040
-
lb
|
$9,010 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs