Assessment Year | 2000 |
---|---|
Principal Product | Chemicals |
NAICS |
n/a
|
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $10 M to 50M |
# of Employees | 32 |
Plant Area |
70,000
ft2
|
Annual Production | 45,000,000
lb
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $222,825 | 4,898,300 |
kWh
|
$0.045 |
Electricity Demand | $19,979 | 830 |
kW-mo/yr
|
$24.07 |
Electricity Fees | $30,603 | - |
|
- |
Natural Gas | $287,091 | 89,180 |
MMBtu
|
$3.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,095 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,722 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,608 | $3,457 |
$1,488
28,722
kWh
|
$120
-
kW-mo/yr
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $9,212 | $8,200 |
$8,562
165,299
kWh
|
$650
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $594 | $122 |
$546
10,551
kWh
|
$48
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $373 | $40 |
$349
6,741
kWh
|
$24
-
kW-mo/yr
|
- | - | |
05 | 3.7198: Reduce / eliminate use of disposable product | $460 | $900 | - | - |
$460
-
lb
|
- | |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $9,720 | - | - | - | - | $9,720 | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $9,128 | $3,700 | - | - | - | $9,128 | |
TOTAL RECOMMENDED | $31,095 | $16,419 |
$10,945
211,313
kWh
|
$842
-
kW-mo/yr
|
$460
-
lb
|
$18,848 | ||
TOTAL IMPLEMENTED | $30,722 | $16,379 |
$10,596
204,572
kWh
|
$818
-
kW-mo/yr
|
$460
-
lb
|
$18,848 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs