| Assessment Year | 2000 |
|---|---|
| Principal Product | Caps |
| NAICS |
n/a
|
| SIC | 2353: Hats, Caps, and Millinery |
| Sales Range | $10 M to 50M |
| # of Employees | 285 |
| Plant Area |
100,000
ft2
|
| Annual Production | 1,897,200
pieces
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $93,617 | 1,423,505 |
kWh
|
$0.066 |
| Electricity Fees | $6,044 | - |
|
- |
| Natural Gas | $5,710 | 1,148 |
MMBtu
|
$4.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $43,805 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,601 | $3,622 |
$1,601
22,860
kWh
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $3,183 | $2,350 |
$3,183
45,428
kWh
|
- | - | - | |
| 03 | 2.4314: Use synthetic lubricant | $226 | $180 |
$226
3,224
kWh
|
- | - | - | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $5,769 | $2,330 |
$5,769
82,356
kWh
|
- | - | - | |
| 05 | 3.5313: Increase amount of waste recovered for resale | $358 | - | - |
$358
-
lb
|
- | - | |
| 06 | 3.7198: Reduce / eliminate use of disposable product | $194 | $120 | - |
$194
-
lb
|
- | - | |
| 07 | 4.611: Begin a practice of predictive / preventative maintenance | $18,160 | $3,700 | - | - | $18,160 | - | |
| 08 | 4.445: Install equipment to move product | $14,183 | $2,580 | - | - | - | $14,183 | |
| 09 | 3.8132: Use less toxic and volatile solvent substitutes | $131 | - | - | - | - | $131 | |
| TOTAL RECOMMENDED | $43,805 | $14,882 |
$10,779
153,868
kWh
|
$552
-
lb
|
$18,160 | $14,314 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs