ITAC Assessment: MO0262
ITAC logo
ITAC Assessment: MO0262
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Truck Engine Oil Coolers
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 128,420
ft2
Annual Production 114,000
units
Production Hrs. Annual 6,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $196,186 5,342,907
kWh
Electricity Demand $82,944 1,812
kW-mo/yr
Electricity Fees $31,179 -
Natural Gas $45,779 12,795
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $90,605 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $67,488

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $4,918 $100 $4,172
98,183
kWh
$746
-
kW-mo/yr
- - - -
02 2.1113: Reduce combustion air flow to optimum $417 $500 - - $417
-
MMBtu
- - -
03 3.5316: Contract a wood pallet recycling company $5,100 - - - - $5,100
-
lb
- -
04 3.5248: Separate and recycle scrap metal to foundry or for sale $57,053 - - - - - - $57,053
05 4.431: Train operators for maximum operating efficiency $23,117 $30,000 - - - - $23,117 -
TOTAL RECOMMENDED $90,605 $30,600 $4,172
98,183
kWh
$746
-
kW-mo/yr
$417
-
MMBtu
$5,100
-
lb
$23,117 $57,053
TOTAL IMPLEMENTED $67,488 $600 $4,172
98,183
kWh
$746
-
kW-mo/yr
$417
-
MMBtu
$5,100
-
lb
- $57,053
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs