| Assessment Year | 2012 |
|---|---|
| Principal Product | Valve assemblies |
| NAICS | 332919: Other Metal Valve and Pipe Fitting Manufacturing |
| SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 110 |
| Plant Area |
60,000
ft2
|
| Annual Production | 60,000
pieces
|
| Production Hrs. Annual | 6,279
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $146,607 | 2,253,015 |
kWh
|
$0.065 |
| Electricity Demand | $48,472 | 6,974 |
kW-mo/yr
|
$6.95 |
| Electricity Fees | $1,617 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $31,295 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,210 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,100 | $33,600 |
$14,200
253,200
kWh
|
$2,900
-
kW-mo/yr
|
- | - | |
| 02 | 2.3212: Optimize plant power factor | $5,450 | $18,900 | - |
$5,450
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,375 | $2,490 |
$5,375
96,000
kWh
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $960 | $440 |
$150
2,660
kWh
|
$20
-
kW-mo/yr
|
$790 | - | |
| 05 | 2.7135: Install occupancy sensors | $850 | $381 |
$850
15,155
kWh
|
- | - | - | |
| 06 | 2.7135: Install occupancy sensors | $605 | - |
$460
8,270
kWh
|
$145
-
kW-mo/yr
|
- | - | |
| 07 | 2.7135: Install occupancy sensors | $280 | $381 |
$280
5,000
kWh
|
- | - | - | |
| 08 | 2.8123: Pay utility bills on time | $675 | - | - | - | - | $675 | |
| TOTAL RECOMMENDED | $31,295 | $56,192 |
$21,315
380,285
kWh
|
$8,515
-
kW-mo/yr
|
$790 | $675 | ||
| TOTAL IMPLEMENTED | $24,210 | $36,852 |
$21,165
377,625
kWh
|
$3,045
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs