ITAC Assessment: AM0604
ITAC logo
ITAC Assessment: AM0604
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Valve assemblies
NAICS 332919: Other Metal Valve and Pipe Fitting Manufacturing
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 60,000
ft2
Annual Production 60,000
pieces
Production Hrs. Annual 6,279
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $146,607 2,253,015
kWh
Electricity Demand $48,472 6,974
kW-mo/yr
Electricity Fees $1,617 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,295 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,210

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $17,100 $33,600 $14,200
253,200
kWh
$2,900
-
kW-mo/yr
- -
02 2.3212: Optimize plant power factor $5,450 $18,900 - $5,450
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,375 $2,490 $5,375
96,000
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $960 $440 $150
2,660
kWh
$20
-
kW-mo/yr
$790 -
05 2.7135: Install occupancy sensors $850 $381 $850
15,155
kWh
- - -
06 2.7135: Install occupancy sensors $605 - $460
8,270
kWh
$145
-
kW-mo/yr
- -
07 2.7135: Install occupancy sensors $280 $381 $280
5,000
kWh
- - -
08 2.8123: Pay utility bills on time $675 - - - - $675
TOTAL RECOMMENDED $31,295 $56,192 $21,315
380,285
kWh
$8,515
-
kW-mo/yr
$790 $675
TOTAL IMPLEMENTED $24,210 $36,852 $21,165
377,625
kWh
$3,045
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs