| Assessment Year | 1999 |
|---|---|
| Principal Product | Electric Household Appliances |
| NAICS |
n/a
|
| SIC | 3634: Electric Housewares and Fans |
| Sales Range | $50 M to 100M |
| # of Employees | 450 |
| Plant Area |
225,000
ft2
|
| Annual Production | 5,200,000
pieces
|
| Production Hrs. Annual | 2,450
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $153,777 | 3,358,441 |
kWh
|
$0.046 |
| Electricity Demand | $25,547 | 1,101 |
kW-mo/yr
|
$23.20 |
| Electricity Fees | $21,720 | - |
|
- |
| Natural Gas | $129,505 | 37,522 |
MMBtu
|
$3.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $79,773 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,773 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,831 | - |
$5,787
110,785
kWh
|
$1,044
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $1,596 | - |
$1,271
24,326
kWh
|
$325
-
kW-mo/yr
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $2,342 | - |
$1,715
32,825
kWh
|
$627
-
kW-mo/yr
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $990 | - |
$735
14,068
kWh
|
$255
-
kW-mo/yr
|
- | - | |
| 05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $27,000 | - | - | - |
$27,000
-
lb
|
- | |
| 06 | 3.5316: Contract a wood pallet recycling company | $18,130 | - | - | - |
$18,130
-
lb
|
- | |
| 07 | 4.611: Begin a practice of predictive / preventative maintenance | $11,004 | - | - | - | - | $11,004 | |
| 08 | 4.422: Utilize outside contracting | $11,880 | - | - | - | - | $11,880 | |
| TOTAL RECOMMENDED | $79,773 | - |
$9,508
182,004
kWh
|
$2,251
-
kW-mo/yr
|
$45,130
-
lb
|
$22,884 | ||
| TOTAL IMPLEMENTED | $21,773 | - |
$8,773
167,936
kWh
|
$1,996
-
kW-mo/yr
|
- | $11,004 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs