ITAC Assessment: MO0253
ITAC logo
ITAC Assessment: MO0253
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Bearings and Bushings
NAICS
n/a
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 92
Plant Area 41,500
ft2
Annual Production 300,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,096 2,789,273
kWh
Electricity Demand $26,823 499
kW-mo/yr
Electricity Fees $15,448 -
Natural Gas $47,037 8,065
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $88,818 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,901

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $4,142 $5,326 $3,336
82,649
kWh
$806
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,507 $5,843 $2,023
50,117
kWh
$484
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,044 $40 $1,668
41,325
kWh
$376
-
kW-mo/yr
- -
04 2.4221: Install compressor air intakes in coolest locations $1,393 $58 $1,124
27,843
kWh
$269
-
kW-mo/yr
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,322 - $1,053
26,084
kWh
$269
-
kW-mo/yr
- -
06 4.652: Replace existing equipment with more suitable substitutes $63,081 $12,600 - - - $63,081
07 4.611: Begin a practice of predictive / preventative maintenance $14,000 $3,700 - - - $14,000
08 2.1311: Replace electrically-operated equipment with fossil fuel equipment $329 $714 - - $329 -
TOTAL RECOMMENDED $88,818 $28,281 $9,204
228,018
kWh
$2,204
-
kW-mo/yr
$329 $77,081
TOTAL IMPLEMENTED $22,901 $9,124 $7,181
177,901
kWh
$1,720
-
kW-mo/yr
- $14,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs