ITAC Assessment: MO0251
ITAC logo
ITAC Assessment: MO0251
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Rotors
NAICS
n/a
SIC 3621: Motors and Generators
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 35,200
ft2
Annual Production 38,000,000
pieces
Production Hrs. Annual 4,466
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,054 4,984,467
kWh
Electricity Demand $87,821 1,028
kW-mo/yr
Electricity Fees $9,135 -
Natural Gas $19,226 4,199
MMBtu
LPG $2,793 95
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,492 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,264

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 4.423: Move product using mechanical means $1,228 $3,360 - - - $1,228
02 4.513: Re-arrange equipment layout to reduce labor costs $900 $1,831 - - - $900
03 4.126: Install sensors to detect defects $27,239 $13,276 - - - $27,239
04 2.4221: Install compressor air intakes in coolest locations $910 $100 $483
27,257
kWh
$427
-
kW-mo/yr
- -
05 2.4133: Use most efficient type of electric motors $1,713 $3,862 $773
43,669
kWh
$940
-
kW-mo/yr
- -
06 3.5313: Increase amount of waste recovered for resale $15,502 $17,960 - - $15,502
-
lb
-
TOTAL RECOMMENDED $47,492 $40,389 $1,256
70,926
kWh
$1,367
-
kW-mo/yr
$15,502
-
lb
$29,367
TOTAL IMPLEMENTED $46,264 $37,029 $1,256
70,926
kWh
$1,367
-
kW-mo/yr
$15,502
-
lb
$28,139
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs