ITAC Assessment: MO0250
ITAC logo
ITAC Assessment: MO0250
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Aeration Equipment
NAICS
n/a
SIC 3589: Service Industry Machinery, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 36
Plant Area 51,000
ft2
Annual Production 260,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $12,786 297,479
kWh
Electricity Demand $7,430 156
kW-mo/yr
Electricity Fees $2,932 -
Natural Gas $8,702 1,512
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,470 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,982

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 4.652: Replace existing equipment with more suitable substitutes $815 $587 - - - $815
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,026 $5,915 $1,548
29,308
kWh
$478
-
kW-mo/yr
- -
03 2.4221: Install compressor air intakes in coolest locations $141 $104 $93
1,758
kWh
$48
-
kW-mo/yr
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $(-62.0) $622 $(-62.0)
(-1,172)
kWh
- - -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $840 - - - $840
-
lb
-
06 3.5316: Contract a wood pallet recycling company $1,710 - - - $1,710
-
lb
-
TOTAL RECOMMENDED $5,470 $7,228 $1,579
29,894
kWh
$526
-
kW-mo/yr
$2,550
-
lb
$815
TOTAL IMPLEMENTED $2,982 $6,606 $1,641
31,066
kWh
$526
-
kW-mo/yr
- $815
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs