Assessment Year | 1995 |
---|---|
Principal Product | Corrugated packing |
NAICS |
n/a
|
SIC | 2670: |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
75,000
ft2
|
Annual Production | 3,000
ton
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,944 | 1,051,876 |
kWh
|
$0.047 |
Natural Gas | $41,887 | 8,252 |
MMBtu
|
$5.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,539 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,666 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,303 | $450 |
$3,303
79,426
kWh
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $186 | $115 |
$186
4,396
kWh
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $441 | $71 |
$441
10,258
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,710 | $666 |
$3,710
89,097
kWh
|
- | - | |
05 | 2.2511: Insulate bare equipment | $848 | $299 | - |
$848
-
MMBtu
|
- | |
06 | 2.2511: Insulate bare equipment | $842 | $268 | - |
$842
-
MMBtu
|
- | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,848 | $600 | - |
$1,848
-
MMBtu
|
- | |
08 | 2.2531: Re-size charging openings or add movable cover or door | $1,473 | $2,500 | - |
$1,473
-
MMBtu
|
- | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,888 | - | - | - |
$3,888
-
lb
|
|
TOTAL RECOMMENDED | $16,539 | $4,969 |
$7,640
183,177
kWh
|
$5,011
-
MMBtu
|
$3,888
-
lb
|
||
TOTAL IMPLEMENTED | $8,666 | $935 |
$3,930
94,080
kWh
|
$848
-
MMBtu
|
$3,888
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs