ITAC Assessment: MO0245
ITAC logo
ITAC Assessment: MO0245
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Low Volatage Aluminum Electrical Cable
NAICS
n/a
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $100
M
to 500
M
# of Employees 245
Plant Area 237,450
ft2
Annual Production 45,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $558,678 16,221,571
kWh
Electricity Demand $115,640 2,743
kW-mo/yr
Electricity Fees $33,786 -
Natural Gas $189,057 51,180
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,031 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $48,620

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 4.611: Begin a practice of predictive / preventative maintenance $21,816 $9,450 - - - - $21,816
02 2.4221: Install compressor air intakes in coolest locations $3,742 $77 $3,278
88,804
kWh
$464
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,685 $40 $2,348
63,599
kWh
$337
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $21,238 $33,352 $18,708
506,741
kWh
$2,530
-
kW-mo/yr
- - -
05 3.5217: Reuse / recycle/ sell paper products $23,640 - - - - $23,640
-
lb
-
06 3.3128: Utilize other methods to remove contaminants $910 $1,000 - - $910
-
gal
- -
TOTAL RECOMMENDED $74,031 $43,919 $24,334
659,144
kWh
$3,331
-
kW-mo/yr
$910
-
gal
$23,640
-
lb
$21,816
TOTAL IMPLEMENTED $48,620 $33,429 $21,986
595,545
kWh
$2,994
-
kW-mo/yr
- $23,640
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs