Assessment Year | 2017 |
---|---|
Principal Product | Military Footwear |
NAICS | 316210: Footwear Manufacturing |
SIC | 3149: Footwear, Except Rubber, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 207 |
Plant Area |
148,800
ft2
|
Annual Production | 259,200
units
|
Production Hrs. Annual | 2,375
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $125,507 | 2,004,800 |
kWh
|
$0.063 | |
Electricity Demand | $113,641 | 8,990 |
kW-mo/yr
|
$12.64 | |
Natural Gas | $1,626 | 287 |
MMBtu
|
$5.67 | |
Waste Disposal Costs | |||||
Water Usage | $1,619 | 757,500 |
Tgal
|
$0.002 | |
Water Disposal | $8,272 | 758 |
Tgal
|
$10.92 | |
Solid Waste (non-haz) | $30,000 | 67,000 |
lb
|
$0.45 | |
TOTAL YEARLY COSTS | $280,665 | ||||
RECOMMENDED SAVINGS* | $44,360 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $4,401 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $36,700 | $4,000 | - | - | - |
$36,700
-
lb
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,092 | $3,050 |
$3,092
49,400
kWh
|
- | - | - | - | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $1,404 | $6,000 |
$1,404
22,425
kWh
|
- | - | - | - | |
04 | 2.6218: Turn off equipment when not in use | $1,211 | $25 |
$1,211
19,350
kWh
|
- | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,190 | $3,450 |
$1,095
17,497
kWh
|
$95
-
kW-mo/yr
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $665 | $750 | - | - |
$665
-
MMBtu
|
- | - | |
07 | 4.812: Apply for investment incentives | $98 | $20 | - | - | - | - | $98 | |
TOTAL RECOMMENDED | $44,360 | $17,295 |
$6,802
108,672
kWh
|
$95
-
kW-mo/yr
|
$665
-
MMBtu
|
$36,700
-
lb
|
$98 | ||
TOTAL IMPLEMENTED | $4,401 | $3,095 |
$4,303
68,750
kWh
|
- | - | - | $98 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs