ITAC Assessment: MO0234
ITAC logo
ITAC Assessment: MO0234
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Combat Boots
NAICS
n/a
SIC 3143: Men's Footwear, Except Athletic
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 113,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $137,743 2,854,631
kWh
Electricity Demand $95,504 1,091
kW-mo/yr
Electricity Fees $37,738 -
Natural Gas $10,503 1,886
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $77,171 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,678

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 4.611: Begin a practice of predictive / preventative maintenance $11,260 $3,700 - - - - $11,260
02 2.4221: Install compressor air intakes in coolest locations $894 $45 $631
10,258
kWh
$263
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $752 $40 $577
9,379
kWh
$175
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $3,772 $5,673 $2,721
44,256
kWh
$1,051
-
kW-mo/yr
- - -
05 3.5311: Recover and reuse waste material $60,000 - - - - $60,000
-
lb
-
06 3.7214: Reduce or eliminate waste $493 $192 - - $493
-
gal
- -
TOTAL RECOMMENDED $77,171 $9,650 $3,929
63,893
kWh
$1,489
-
kW-mo/yr
$493
-
gal
$60,000
-
lb
$11,260
TOTAL IMPLEMENTED $16,678 $9,458 $3,929
63,893
kWh
$1,489
-
kW-mo/yr
- - $11,260
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs