Assessment Year | 1998 |
---|---|
Principal Product | Combat Boots |
NAICS |
n/a
|
SIC | 3143: Men's Footwear, Except Athletic |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
113,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $137,743 | 2,854,631 |
kWh
|
$0.048 |
Electricity Demand | $95,504 | 1,091 |
kW-mo/yr
|
$87.54 |
Electricity Fees | $37,738 | - |
|
- |
Natural Gas | $10,503 | 1,886 |
MMBtu
|
$5.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,171 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,678 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.611: Begin a practice of predictive / preventative maintenance | $11,260 | $3,700 | - | - | - | - | $11,260 | |
02 | 2.4221: Install compressor air intakes in coolest locations | $894 | $45 |
$631
10,258
kWh
|
$263
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $752 | $40 |
$577
9,379
kWh
|
$175
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $3,772 | $5,673 |
$2,721
44,256
kWh
|
$1,051
-
kW-mo/yr
|
- | - | - | |
05 | 3.5311: Recover and reuse waste material | $60,000 | - | - | - | - |
$60,000
-
lb
|
- | |
06 | 3.7214: Reduce or eliminate waste | $493 | $192 | - | - |
$493
-
gal
|
- | - | |
TOTAL RECOMMENDED | $77,171 | $9,650 |
$3,929
63,893
kWh
|
$1,489
-
kW-mo/yr
|
$493
-
gal
|
$60,000
-
lb
|
$11,260 | ||
TOTAL IMPLEMENTED | $16,678 | $9,458 |
$3,929
63,893
kWh
|
$1,489
-
kW-mo/yr
|
- | - | $11,260 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs