ITAC Assessment: MO0230
ITAC logo
ITAC Assessment: MO0230
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product RTA (Ready-to Assembly) Furniture
NAICS
n/a
SIC 2511: Wood Household Furniture, Except Upholstered
Sales Range $50
M
to 100
M
# of Employees 500
Plant Area 500,000
ft2
Annual Production 1,800,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $366,747 7,401,231
kWh
Electricity Demand $42,367 1,765
kW-mo/yr
Electricity Fees $54,756 -
Natural Gas $148,399 46,108
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $273,803 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $161,592

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 3.1191: Change procedures / equipment / operating conditions $86,930 $91,375 - - - $86,930
02 4.611: Begin a practice of predictive / preventative maintenance $16,820 $3,500 - - - $16,820
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,021 $1,297 $1,853
32,532
kWh
$168
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $408 $690 $384
6,741
kWh
$24
-
kW-mo/yr
- -
05 2.4221: Install compressor air intakes in coolest locations $3,259 $160 $2,971
52,169
kWh
$288
-
kW-mo/yr
- -
06 2.4314: Use synthetic lubricant $1,463 $622 $1,319
23,154
kWh
$144
-
kW-mo/yr
- -
07 2.4133: Use most efficient type of electric motors $4,263 $7,769 $3,855
67,702
kWh
$408
-
kW-mo/yr
- -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,546 - $1,402
24,619
kWh
$144
-
kW-mo/yr
- -
09 3.1191: Change procedures / equipment / operating conditions $93,928 $39,600 - - $93,928
-
lb
-
10 3.1191: Change procedures / equipment / operating conditions $63,165 $15,100 - - $63,165
-
lb
-
TOTAL RECOMMENDED $273,803 $160,113 $11,784
206,917
kWh
$1,176
-
kW-mo/yr
$157,093
-
lb
$103,750
TOTAL IMPLEMENTED $161,592 $116,391 $10,465
183,763
kWh
$1,032
-
kW-mo/yr
$63,165
-
lb
$86,930
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs