| Assessment Year | 1998 |
|---|---|
| Principal Product | Various Colors of Ink |
| NAICS |
n/a
|
| SIC | 2893: Printing Ink |
| Sales Range | $50 M to 100M |
| # of Employees | 70 |
| Plant Area |
80,000
ft2
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $110,224 | 2,144,197 |
kWh
|
$0.051 |
| Electricity Demand | $12,632 | 520 |
kW-mo/yr
|
$24.29 |
| Electricity Fees | $16,103 | - |
|
- |
| Natural Gas | $34,342 | 5,835 |
MMBtu
|
$5.89 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $3,138,778 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,639 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.1191: Change procedures / equipment / operating conditions | $3,111,888 | - | - | - | - | $3,111,888 | |
| 02 | 4.611: Begin a practice of predictive / preventative maintenance | $11,035 | $3,700 | - | - | - | $11,035 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,548 | $7,376 |
$3,160
53,634
kWh
|
$388
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $708 | $1,568 |
$587
9,965
kWh
|
$121
-
kW-mo/yr
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,899 | $40 |
$2,729
46,307
kWh
|
$170
-
kW-mo/yr
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $1,496 | $52 |
$1,399
23,740
kWh
|
$97
-
kW-mo/yr
|
- | - | |
| 07 | 2.4133: Use most efficient type of electric motors | $6,484 | $6,161 |
$6,096
103,458
kWh
|
$388
-
kW-mo/yr
|
- | - | |
| 08 | 3.6192: Use a less expensive method of waste removal | $720 | $2,080 | - | - |
$720
-
lb
|
- | |
| TOTAL RECOMMENDED | $3,138,778 | $20,977 |
$13,971
237,104
kWh
|
$1,164
-
kW-mo/yr
|
$720
-
lb
|
$3,122,923 | ||
| TOTAL IMPLEMENTED | $13,639 | $15,145 |
$12,572
213,364
kWh
|
$1,067
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs