Assessment Year | 1998 |
---|---|
Principal Product | Packaged Printing Products |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
160,000
ft2
|
Annual Production | 114,000,000
pieces
|
Production Hrs. Annual | 6,860
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,568 | 2,371,923 |
kWh
|
$0.023 |
Electricity Demand | $51,620 | 540 |
kW-mo/yr
|
$95.59 |
Electricity Fees | $13,598 | - |
|
- |
Natural Gas | $17,522 | 2,311 |
MMBtu
|
$7.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $112,975 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $102,584 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.711: Initiate a total quality management program | $16,686 | $25,000 | - | - | - | $16,686 | |
02 | 4.432: Cross-train personnel to avoid lost time | $14,518 | $25,000 | - | - | - | $14,518 | |
03 | 4.514: Re-arrange equipment layout to reduce handling costs | $4,800 | $10,000 | - | - | - | $4,800 | |
04 | 4.611: Begin a practice of predictive / preventative maintenance | $2,970 | $3,500 | - | - | - | $2,970 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,859 | $8,528 |
$2,253
79,426
kWh
|
$1,606
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $974 | $1,566 |
$515
18,171
kWh
|
$459
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,305 | $40 |
$2,795
98,769
kWh
|
$1,510
-
kW-mo/yr
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $1,359 | $53 |
$881
31,067
kWh
|
$478
-
kW-mo/yr
|
- | - | |
09 | 2.4133: Use most efficient type of electric motors | $886 | $378 |
$551
19,343
kWh
|
$335
-
kW-mo/yr
|
- | - | |
10 | 3.1163: Use plastic pallets instead of wood | $61,750 | $84,375 | - | - |
$61,750
-
lb
|
- | |
11 | 3.7196: Use re-usable filters | $868 | $2,079 | - | - |
$868
-
lb
|
- | |
TOTAL RECOMMENDED | $112,975 | $160,519 |
$6,995
246,776
kWh
|
$4,388
-
kW-mo/yr
|
$62,618
-
lb
|
$38,974 | ||
TOTAL IMPLEMENTED | $102,584 | $149,819 |
$1,066
37,514
kWh
|
$794
-
kW-mo/yr
|
$61,750
-
lb
|
$38,974 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs