Assessment Year | 1997 |
---|---|
Principal Product | Food Service Equipment |
NAICS |
n/a
|
SIC | 3430: |
Sales Range | $10 M to 50M |
# of Employees | 157 |
Plant Area |
62,500
ft2
|
Annual Production | 192,000
pieces
|
Production Hrs. Annual | 6,292
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $63,826 | 1,427,022 |
kWh
|
$0.045 |
Electricity Demand | $8,994 | 286 |
kW-mo/yr
|
$31.45 |
Electricity Fees | $8,994 | - |
|
- |
Natural Gas | $17,082 | 2,981 |
MMBtu
|
$5.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $90,531 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,066 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.611: Begin a practice of predictive / preventative maintenance | $5,391 | $3,500 | - | - | - | - | $5,391 | |
02 | 4.514: Re-arrange equipment layout to reduce handling costs | $5,000 | $12,500 | - | - | - | - | $5,000 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $780 | $2,032 |
$687
13,482
kWh
|
$93
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,526 | $1,222 |
$6,011
117,819
kWh
|
$515
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $144 | $276 |
$136
2,638
kWh
|
$8
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $541 | $40 |
$464
9,086
kWh
|
$77
-
kW-mo/yr
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $553 | $50 |
$473
9,379
kWh
|
$80
-
kW-mo/yr
|
- | - | - | |
08 | 2.4133: Use most efficient type of electric motors | $1,288 | $1,976 |
$1,171
22,860
kWh
|
$117
-
kW-mo/yr
|
- | - | - | |
09 | 2.4321: Upgrade obsolete equipment | $55,000 | $85,000 | - | - |
$55,000
-
gal
|
- | - | |
10 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $15,308 | $4,860 | - | - | - |
$15,308
-
lb
|
- | |
TOTAL RECOMMENDED | $90,531 | $111,456 |
$8,942
175,264
kWh
|
$890
-
kW-mo/yr
|
$55,000
-
gal
|
$15,308
-
lb
|
$10,391 | ||
TOTAL IMPLEMENTED | $34,066 | $24,108 |
$7,655
150,058
kWh
|
$712
-
kW-mo/yr
|
- |
$15,308
-
lb
|
$10,391 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs