| Assessment Year | 1996 |
|---|---|
| Principal Product | Automatic Pull-Cable Parts |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $1 M to 5M |
| # of Employees | 500 |
| Plant Area |
10,500
ft2
|
| Annual Production | 2,000
ton
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $34,699 | 598,769 |
kWh
|
$0.058 |
| Electricity Demand | $3,178 | 1,485 |
kW-mo/yr
|
$2.14 |
| Natural Gas | $5,897 | 849 |
MMBtu
|
$6.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $54,498 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $52,943 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.1162: Use less wasteful packaging | $50,000 | $94,219 | - | - |
$50,000
-
lb
|
|
| 02 | 2.4221: Install compressor air intakes in coolest locations | $788 | $90 |
$753
12,896
kWh
|
$35
-
kW-mo/yr
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $476 | $40 |
$455
7,913
kWh
|
$21
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $684 | $840 |
$644
11,137
kWh
|
$40
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $342 | $274 |
$321
5,569
kWh
|
$21
-
kW-mo/yr
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $142 | - |
$136
2,345
kWh
|
$6
-
kW-mo/yr
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $1,917 | $3,722 |
$1,832
31,653
kWh
|
$85
-
kW-mo/yr
|
- | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $149 | - |
$143
2,345
kWh
|
$6
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $54,498 | $99,185 |
$4,284
73,858
kWh
|
$214
-
kW-mo/yr
|
$50,000
-
lb
|
||
| TOTAL IMPLEMENTED | $52,943 | $99,055 |
$2,797
48,359
kWh
|
$146
-
kW-mo/yr
|
$50,000
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs