ITAC Assessment: MO0183
ITAC logo
ITAC Assessment: MO0183
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Packaged Aerosols and Fluids
NAICS
n/a
SIC 2842: Specialty Cleaning, Polishing, and Sanitation Preparations
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 130,000
ft2
Annual Production 15,000,000
pieces
Production Hrs. Annual 2,496
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $99,613 1,740,621
kWh
Electricity Demand $9,795 5,330
kW-mo/yr
Natural Gas $35,156 8,191
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,033 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,174

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,065 $1,949 $953
16,706
kWh
$112
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,658 $6,064 $2,378
41,618
kWh
$280
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $320 - $307
5,275
kWh
$13
-
kW-mo/yr
- -
04 2.4221: Install compressor air intakes in coolest locations $3,780 $160 $3,530
61,841
kWh
$250
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,871 $65 $2,682
46,893
kWh
$189
-
kW-mo/yr
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,579 $100 $1,474
25,791
kWh
$105
-
kW-mo/yr
- -
07 2.4235: Remove or close off unneeded compressed air lines $325 $60 $190
3,224
kWh
$135
-
kW-mo/yr
- -
08 2.4133: Use most efficient type of electric motors $1,309 $3,205 $1,214
21,102
kWh
$95
-
kW-mo/yr
- -
09 2.6212: Turn off equipment during breaks, reduce operating time $76 - $44
879
kWh
$32
-
kW-mo/yr
- -
10 4.211: Consider use / purchase of bulk materials where possible $19,050 $180 - - $2,050
-
lb
$17,000
TOTAL RECOMMENDED $33,033 $11,783 $12,772
223,329
kWh
$1,211
-
kW-mo/yr
$2,050
-
lb
$17,000
TOTAL IMPLEMENTED $23,174 $8,253 $3,565
62,427
kWh
$559
-
kW-mo/yr
$2,050
-
lb
$17,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs