Assessment Year | 1996 |
---|---|
Principal Product | Telephone pedestals |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 132 |
Plant Area |
112,000
ft2
|
Annual Production | 15,000,000
lb
|
Production Hrs. Annual | 4,488
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,643 | 1,614,009 |
kWh
|
$0.054 |
Electricity Demand | $13,935 | 2,798 |
kW-mo/yr
|
$4.98 |
LPG | $68,465 | 13,262 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,043 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $53,861 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $944 | $1,390 |
$758
14,068
kWh
|
$186
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,797 | $3,616 |
$1,436
26,671
kWh
|
$361
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $142 | - |
$126
2,345
kWh
|
$16
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $294 | - |
$241
4,396
kWh
|
$53
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $2,324 | $5,161 |
$1,905
35,463
kWh
|
$419
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,040 | $160 |
$2,493
46,600
kWh
|
$547
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $2,598 | $35 |
$2,131
39,859
kWh
|
$467
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.1332: Convert combustion equipment to burn natural gas | $41,832 | $4,430 | - | - |
$(-26,633.0)
-
MMBtu
|
$68,465
-
MMBtu
|
- | - | |
09 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $1,724 | $130 | - | - | - | - |
$1,724
-
lb
|
- | |
10 | 3.5316: Contract a wood pallet recycling company | $840 | $1,000 | - | - | - | - |
$840
-
lb
|
- | |
11 | 2.8114: Change rate schedules or other changes in utility service | $1,508 | $4,890 | - | - | - | - | - |
$1,508
-
Tgal
|
|
TOTAL RECOMMENDED | $57,043 | $20,812 |
$9,090
169,402
kWh
|
$2,049
-
kW-mo/yr
|
$(-26,633.0)
-
MMBtu
|
$68,465
-
MMBtu
|
$2,564
-
lb
|
$1,508
-
Tgal
|
||
TOTAL IMPLEMENTED | $53,861 | $20,652 |
$6,471
120,457
kWh
|
$1,486
-
kW-mo/yr
|
$(-26,633.0)
-
MMBtu
|
$68,465
-
MMBtu
|
$2,564
-
lb
|
$1,508
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs