ITAC Assessment: MO0171
ITAC logo
ITAC Assessment: MO0171
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Remanufactured Diesel Engines
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 336
Plant Area 67,200
ft2
Annual Production 10,000
units
Production Hrs. Annual 6,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $77,002 3,055,979
kWh
Electricity Demand $37,192 6,792
kW-mo/yr
Natural Gas $77,531 18,596
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,279 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,329

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings By-product Production Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,139 $6,136 $2,254
76,202
kWh
$885
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $172 - $139
4,689
kWh
$33
-
kW-mo/yr
- - - -
03 2.4221: Install compressor air intakes in coolest locations $1,375 $174 $1,024
34,584
kWh
$351
-
kW-mo/yr
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $208 $100 $155
5,275
kWh
$53
-
kW-mo/yr
- - - -
05 2.8113: Purchase gas directly from a contract gas supplier $16,272 $2,280 - - - - $16,272 -
06 2.2424: Use heat in flue gases to preheat products or materials $303 $850 - - $303
-
MMBtu
- - -
07 3.5311: Recover and reuse waste material $810 $100 - - - $450
-
lb
- $360
TOTAL RECOMMENDED $22,279 $9,640 $3,572
120,750
kWh
$1,322
-
kW-mo/yr
$303
-
MMBtu
$450
-
lb
$16,272 $360
TOTAL IMPLEMENTED $4,329 $6,336 $2,548
86,166
kWh
$971
-
kW-mo/yr
- $450
-
lb
- $360
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs