Assessment Year | 1996 |
---|---|
Principal Product | Remanufactured Diesel Engines |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 336 |
Plant Area |
67,200
ft2
|
Annual Production | 10,000
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $77,002 | 3,055,979 |
kWh
|
$0.025 |
Electricity Demand | $37,192 | 6,792 |
kW-mo/yr
|
$5.48 |
Natural Gas | $77,531 | 18,596 |
MMBtu
|
$4.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,279 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,329 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,139 | $6,136 |
$2,254
76,202
kWh
|
$885
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $172 | - |
$139
4,689
kWh
|
$33
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,375 | $174 |
$1,024
34,584
kWh
|
$351
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $208 | $100 |
$155
5,275
kWh
|
$53
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.8113: Purchase gas directly from a contract gas supplier | $16,272 | $2,280 | - | - | - | - | $16,272 | - | |
06 | 2.2424: Use heat in flue gases to preheat products or materials | $303 | $850 | - | - |
$303
-
MMBtu
|
- | - | - | |
07 | 3.5311: Recover and reuse waste material | $810 | $100 | - | - | - |
$450
-
lb
|
- | $360 | |
TOTAL RECOMMENDED | $22,279 | $9,640 |
$3,572
120,750
kWh
|
$1,322
-
kW-mo/yr
|
$303
-
MMBtu
|
$450
-
lb
|
$16,272 | $360 | ||
TOTAL IMPLEMENTED | $4,329 | $6,336 |
$2,548
86,166
kWh
|
$971
-
kW-mo/yr
|
- |
$450
-
lb
|
- | $360 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs