Assessment Year | 1996 |
---|---|
Principal Product | High Quality Printed Material |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 98 |
Plant Area |
64,000
ft2
|
Annual Production | 6,100,000
lb
|
Production Hrs. Annual | 5,304
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $131,544 | 2,470,106 |
kWh
|
$0.053 |
Electricity Demand | $16,132 | 7,377 |
kW-mo/yr
|
$2.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,011 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,529 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $3,417 | $6,227 |
$3,196
53,927
kWh
|
$221
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $482 | $43 |
$446
7,620
kWh
|
$36
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,560 | $109 |
$1,446
24,326
kWh
|
$114
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,649 | $10,288 |
$8,972
151,524
kWh
|
$677
-
kW-mo/yr
|
- | |
05 | 2.2437: Recover waste heat from equipment | $1,443 | $3,700 |
$1,443
24,326
kWh
|
- | - | |
06 | 3.5121: Recycle waste ink and cleanup solvent | $6,460 | - | - | - |
$6,460
-
gal
|
|
TOTAL RECOMMENDED | $23,011 | $20,367 |
$15,503
261,723
kWh
|
$1,048
-
kW-mo/yr
|
$6,460
-
gal
|
||
TOTAL IMPLEMENTED | $22,529 | $20,324 |
$15,057
254,103
kWh
|
$1,012
-
kW-mo/yr
|
$6,460
-
gal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs