Assessment Year | 1996 |
---|---|
Principal Product | Urethane, Epoxy, and other coatings |
NAICS |
n/a
|
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
135,000
ft2
|
Annual Production | 700
Tgal
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $110,159 | 2,062,134 |
kWh
|
$0.053 |
Electricity Demand | $12,992 | 5,685 |
kW-mo/yr
|
$2.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,938 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,394 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,288 | $1,980 |
$1,145
18,171
kWh
|
$143
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,040 | $5,272 |
$2,703
42,497
kWh
|
$337
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $265 | - |
$255
4,103
kWh
|
$10
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $810 | $65 |
$745
11,723
kWh
|
$65
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,504 | $60 |
$2,244
35,463
kWh
|
$260
-
kW-mo/yr
|
- | |
06 | 2.4314: Use synthetic lubricant | $599 | $69 |
$538
8,499
kWh
|
$61
-
kW-mo/yr
|
- | |
07 | 2.6121: Reduce hot water temperature to the minimum required | $411 | $60 |
$356
5,569
kWh
|
$55
-
kW-mo/yr
|
- | |
08 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $2,021 | $9,925 | - | - |
$2,021
-
lb
|
|
TOTAL RECOMMENDED | $10,938 | $17,431 |
$7,986
126,025
kWh
|
$931
-
kW-mo/yr
|
$2,021
-
lb
|
||
TOTAL IMPLEMENTED | $5,394 | $12,099 |
$3,039
48,065
kWh
|
$334
-
kW-mo/yr
|
$2,021
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs