ITAC Assessment: MO0149
ITAC logo
ITAC Assessment: MO0149
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product envelopes
NAICS
n/a
SIC 2677: Envelopes
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 150,000
ft2
Annual Production 900,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $214,543 3,572,685
kWh
Natural Gas $10,820 2,307
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,095 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,103

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,105 $1,362 $8,105
138,921
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $10,142 $6,727 $10,142
172,333
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $209 $385 $209
3,810
kWh
04 2.4221: Install compressor air intakes in coolest locations $639 $326 $639
10,844
kWh
05 2.4133: Use most efficient type of electric motors $4,856 $17,800 $4,856
82,063
kWh
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $144 $115 $144
2,345
kWh
TOTAL RECOMMENDED $24,095 $26,715 $24,095
410,316
kWh
TOTAL IMPLEMENTED $23,103 $25,889 $23,103
393,317
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs