ITAC Assessment: MO0143
ITAC logo
ITAC Assessment: MO0143
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product brake shoes and stamping
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 135,585
ft2
Annual Production 25,200,000
pieces
Production Hrs. Annual 6,552
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $146,369 2,938,746
kWh
Natural Gas $32,776 4,918
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,664 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,646

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4221: Install compressor air intakes in coolest locations $4,006 $790 $4,006
61,254
kWh
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $250 $100 $250
3,810
kWh
03 2.4133: Use most efficient type of electric motors $2,256 $3,340 $2,256
37,515
kWh
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,607 $360 $1,607
26,671
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,411 $7,986 $2,411
36,049
kWh
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,134 $470 $1,134
17,292
kWh
TOTAL RECOMMENDED $11,664 $13,046 $11,664
182,591
kWh
TOTAL IMPLEMENTED $7,646 $4,700 $7,646
119,871
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs