Assessment Year | 1993 |
---|---|
Principal Product | Corrugated Cardboard Containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
145,000
ft2
|
Annual Production | 616,159
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $198,232 | 3,171,747 |
kWh
|
$0.062 |
Natural Gas | $143,378 | 40,773 |
MMBtu
|
$3.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $107,038 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,196 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $8,152 | $995 | - |
$8,152
-
MMBtu
|
- | - | |
02 | 2.1222: Install turbulators | $4,111 | $2,000 | - |
$4,111
-
MMBtu
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $8,992 | $17,079 |
$8,992
143,904
kWh
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,357 | $1,085 |
$8,357
133,646
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,056 | $10,520 |
$6,056
97,011
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,528 | $823 |
$3,528
56,565
kWh
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,742 | $1,275 |
$1,742
27,843
kWh
|
- | - | - | |
08 | 2.8113: Purchase gas directly from a contract gas supplier | $60,365 | $300 | - | - | - | $60,365 | |
09 | 3.4114: Replace city water with recycled water via cooling tower | $5,735 | $1,980 |
$(-121.0)
(-2,052)
kWh
|
- |
$5,856
-
Tgal
|
- | |
TOTAL RECOMMENDED | $107,038 | $36,057 |
$28,554
456,917
kWh
|
$12,263
-
MMBtu
|
$5,856
-
Tgal
|
$60,365 | ||
TOTAL IMPLEMENTED | $39,196 | $32,502 |
$26,933
431,126
kWh
|
$12,263
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs