ITAC Assessment: MO0097
ITAC logo
ITAC Assessment: MO0097
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Pharmaceuticals
NAICS
n/a
SIC 2834: Pharmaceutical Preparations
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 90,000
ft2
Annual Production 970,779
lb
Production Hrs. Annual 4,200
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $431,140 10,041,911
kWh
Natural Gas $160,389 47,319
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,793 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,492

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,128 $734 $3,128
72,978
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,250 $18,608 $7,250
169,109
kWh
-
03 2.7135: Install occupancy sensors $4,833 $1,440 $4,833
112,544
kWh
-
04 2.4133: Use most efficient type of electric motors $17,959 $28,210 $17,959
418,523
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,375 $225 $4,375
101,993
kWh
-
06 2.2614: Use cooling tower or economizer to replace chiller cooling $1,468 $2,008 $1,468
34,291
kWh
-
07 2.1233: Analyze flue gas for proper air/fuel ratio $1,153 $1,595 - $1,153
-
MMBtu
08 2.4221: Install compressor air intakes in coolest locations $5,627 $1,200 $5,627
131,008
kWh
-
TOTAL RECOMMENDED $45,793 $54,020 $44,640
1,040,446
kWh
$1,153
-
MMBtu
TOTAL IMPLEMENTED $39,492 $50,572 $38,339
893,611
kWh
$1,153
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs