ITAC Assessment: MO0092
ITAC logo
ITAC Assessment: MO0092
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Men's Suits and Coats
NAICS
n/a
SIC 2311: Men's and Boys' Suits, Coats, and Overcoats
Sales Range $50
M
to 100
M
# of Employees 504
Plant Area 165,000
ft2
Annual Production 250,000
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $352,146 5,712,192
kWh
Natural Gas $41,178 7,791
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,656 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,937

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $16,324 $49,888 $16,324
264,654
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $15,036 $3,642 $15,036
243,845
kWh
-
03 2.4133: Use most efficient type of electric motors $4,452 $14,004 $4,452
72,392
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,401 $1,830 $2,401
38,980
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $3,395 $490 $3,395
55,100
kWh
-
06 2.8113: Purchase gas directly from a contract gas supplier $9,048 $300 - $9,048
TOTAL RECOMMENDED $50,656 $70,154 $41,608
674,971
kWh
$9,048
TOTAL IMPLEMENTED $30,937 $19,776 $21,889
355,217
kWh
$9,048
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs