Assessment Year | 1993 |
---|---|
Principal Product | Die Castings |
NAICS |
n/a
|
SIC | 3365: Aluminum Foundries |
Sales Range | $1 M to 5M |
# of Employees | 24 |
Plant Area |
15,000
ft2
|
Annual Production | 851
pieces
|
Production Hrs. Annual | 6,375
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,915 | 982,122 |
kWh
|
$0.055 |
LPG | $37,828 | 6,447 |
MMBtu
|
$5.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,274 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,955 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $7,157 | $2,995 | - | - | $7,157 | |
02 | 2.8113: Purchase gas directly from a contract gas supplier | $3,319 | - | - | - | $3,319 | |
03 | 2.2511: Insulate bare equipment | $337 | $11 | - |
$337
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $359 | $130 |
$359
6,448
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $691 | $3,036 |
$691
12,603
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $676 | $60 |
$676
12,309
kWh
|
- | - | |
07 | 2.4314: Use synthetic lubricant | $492 | $120 |
$492
9,086
kWh
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $243 | $163 |
$243
4,396
kWh
|
- | - | |
TOTAL RECOMMENDED | $13,274 | $6,515 |
$2,461
44,842
kWh
|
$337
-
MMBtu
|
$10,476 | ||
TOTAL IMPLEMENTED | $9,955 | $6,515 |
$2,461
44,842
kWh
|
$337
-
MMBtu
|
$7,157 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs