ITAC Assessment: MO0055
ITAC logo
ITAC Assessment: MO0055
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product SCRAP METAL PROCESSING
NAICS
n/a
SIC 3341: Secondary Smelting and Refining of Nonferrous Metals
Sales Range $10
M
to 50
M
# of Employees 83
Plant Area
n/a
Annual Production 180,000
ton
Production Hrs. Annual 3,120
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $284,725 3,138,042
kWh
Natural Gas $11,034 2,187
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,497 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,207

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7233: Use properly designed and sized hvac equipment $3,734 $7,535 - $3,734
-
MMBtu
-
02 2.4221: Install compressor air intakes in coolest locations $1,207 $800 $1,207
13,189
kWh
- -
03 2.4312: Improve lubrication practices $1,146 - $1,146
12,603
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $444 $30 $444
4,982
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $175 $339 $217
2,345
kWh
- $(-42.0)
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,657 - $3,657
40,445
kWh
- -
07 2.4133: Use most efficient type of electric motors $134 $2,031 $134
1,465
kWh
- -
TOTAL RECOMMENDED $10,497 $10,735 $6,805
75,029
kWh
$3,734
-
MMBtu
$(-42.0)
TOTAL IMPLEMENTED $1,207 $800 $1,207
13,189
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs