Assessment Year | 1992 |
---|---|
Principal Product | SCRAP METAL PROCESSING |
NAICS |
n/a
|
SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
Sales Range | $10 M to 50M |
# of Employees | 83 |
Plant Area |
n/a
|
Annual Production | 180,000
ton
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $284,725 | 3,138,042 |
kWh
|
$0.091 |
Natural Gas | $11,034 | 2,187 |
MMBtu
|
$5.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,497 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,207 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7233: Use properly designed and sized hvac equipment | $3,734 | $7,535 | - |
$3,734
-
MMBtu
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,207 | $800 |
$1,207
13,189
kWh
|
- | - | |
03 | 2.4312: Improve lubrication practices | $1,146 | - |
$1,146
12,603
kWh
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $444 | $30 |
$444
4,982
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $175 | $339 |
$217
2,345
kWh
|
- | $(-42.0) | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,657 | - |
$3,657
40,445
kWh
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $134 | $2,031 |
$134
1,465
kWh
|
- | - | |
TOTAL RECOMMENDED | $10,497 | $10,735 |
$6,805
75,029
kWh
|
$3,734
-
MMBtu
|
$(-42.0) | ||
TOTAL IMPLEMENTED | $1,207 | $800 |
$1,207
13,189
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs