Assessment Year | 1992 |
---|---|
Principal Product | FOOD SERVICE EQUIPMENT |
NAICS |
n/a
|
SIC | 3556: Food Products Machinery |
Sales Range | $10 M to 50M |
# of Employees | 205 |
Plant Area |
n/a
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 5,339
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $212,240 | 3,073,564 |
kWh
|
$0.069 |
Fuel Oil #2 | $39,187 | 6,905 |
MMBtu
|
$5.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,435 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,636 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,392 | $840 |
$3,643
52,755
kWh
|
- | $(-251.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $841 | $1,015 |
$841
12,309
kWh
|
- | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $17,413 | - |
$22,264
322,392
kWh
|
$(-4,851.0)
-
MMBtu
|
- | |
04 | 2.7494: Install storm windows and doors | $13,673 | $5,500 | - |
$13,673
-
MMBtu
|
- | |
05 | 2.7492: Use proper thickness of insulation on building envelope | $456 | $60 | - |
$456
-
MMBtu
|
- | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,681 | $2,200 | - |
$1,681
-
MMBtu
|
- | |
07 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $43 | $110 | - |
$43
-
MMBtu
|
- | |
08 | 2.4133: Use most efficient type of electric motors | $257 | $1,011 |
$257
8,499
kWh
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $1,200 | $240 |
$1,200
17,292
kWh
|
- | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $479 | - |
$479
7,034
kWh
|
- | - | |
TOTAL RECOMMENDED | $39,435 | $10,976 |
$28,684
420,281
kWh
|
$11,002
-
MMBtu
|
$(-251.0) | ||
TOTAL IMPLEMENTED | $7,636 | $4,405 |
$6,163
89,390
kWh
|
$1,724
-
MMBtu
|
$(-251.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs