ITAC Assessment: MO0047
ITAC logo
ITAC Assessment: MO0047
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product SHOE COMPONENTS
NAICS
n/a
SIC 3131: Boot and Shoe Cut Stock and Findings
Sales Range $10
M
to 50
M
# of Employees 445
Plant Area
n/a
Annual Production 14,868,090
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $283,525 4,567,116
kWh
LPG $23,734 4,841
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,983 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $2,288 $1,906 $2,288
36,928
kWh
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,514 - $2,514
40,445
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,711 - $4,604
74,150
kWh
$(-893.0)
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,380 $2,987 $2,380
38,394
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $2,090 $1,170 $2,090
33,705
kWh
-
TOTAL RECOMMENDED $12,983 $6,063 $13,876
223,622
kWh
$(-893.0)
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs