Assessment Year | 1992 |
---|---|
Principal Product | UNIFORMS |
NAICS |
n/a
|
SIC | 2326: Men's and Boys' Work Clothing |
Sales Range | $5 M to 10M |
# of Employees | 180 |
Plant Area |
n/a
|
Annual Production | 960,000
pieces
|
Production Hrs. Annual | 2,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $76,648 | 1,429,367 |
kWh
|
$0.054 |
LPG | $23,857 | 3,489 |
MMBtu
|
$6.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,474 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,508 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 3.4115: Recover and reuse cooling water | $6,716 | - |
$195
3,517
kWh
|
- | $6,521 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,923 | $586 |
$2,314
43,083
kWh
|
- | $(-391.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $630 | $270 |
$630
11,723
kWh
|
- | - | |
04 | 2.2511: Insulate bare equipment | $3,213 | $672 |
$3,213
59,789
kWh
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $227 | $1,800 |
$227
4,103
kWh
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $76 | - |
$76
1,465
kWh
|
- | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,132 | $1,700 | - |
$1,132
-
MMBtu
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $376 | $234 |
$376
7,034
kWh
|
- | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $181 | $20 |
$181
3,517
kWh
|
- | - | |
TOTAL RECOMMENDED | $14,474 | $5,282 |
$7,212
134,231
kWh
|
$1,132
-
MMBtu
|
$6,130 | ||
TOTAL IMPLEMENTED | $1,508 | $1,934 |
$376
7,034
kWh
|
$1,132
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs