ITAC Assessment: MO0032
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product WOMEN'S SPORTSWEAR
NAICS
n/a
SIC 2339: Women's, Misses', and Juniors' Outerwear, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 113
Plant Area
n/a
Annual Production 185,000
pieces
Production Hrs. Annual 1,875
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,687 225,381
kWh
Natural Gas $16,514 3,896
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,876 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,876

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $519 $92 $519
7,034
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $175 $721 $175
2,345
kWh
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $977 $1,195 - $977
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $1,011 $368 $1,011
13,482
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $168 $50 $168
2,345
kWh
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $26 - $26
293
kWh
-
TOTAL RECOMMENDED $2,876 $2,426 $1,899
25,499
kWh
$977
-
MMBtu
TOTAL IMPLEMENTED $2,876 $2,426 $1,899
25,499
kWh
$977
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs