Assessment Year | 1991 |
---|---|
Principal Product | BUNK BEDS AND HEADBOARDS |
NAICS |
n/a
|
SIC | 2511: Wood Household Furniture, Except Upholstered |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 227,295
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $151,844 | 3,118,406 |
kWh
|
$0.049 |
Wood | $1,440 | 57,223 |
MMBtu
|
$0.025 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,585 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,585 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $673 | $2,931 |
$673
13,482
kWh
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $3,705 | - |
$3,705
74,150
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,369 | $288 |
$1,369
27,550
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $318 | $549 |
$318
6,448
kWh
|
- | |
05 | 2.2627: Use multiple-effect evaporators | $978 | - |
$978
19,637
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $102 | $701 |
$102
2,052
kWh
|
- | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,440 | $300 | - |
$1,440
-
MMBtu
|
|
TOTAL RECOMMENDED | $8,585 | $4,769 |
$7,145
143,319
kWh
|
$1,440
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,585 | $4,769 |
$7,145
143,319
kWh
|
$1,440
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs