| Assessment Year | 1991 |
|---|---|
| Principal Product | CHICKEN PATTIES |
| NAICS |
n/a
|
| SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 400 |
| Plant Area |
n/a
|
| Annual Production | 33,000
ton
|
| Production Hrs. Annual | 5,040
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $608,508 | 11,781,067 |
kWh
|
$0.052 |
| Natural Gas | $198,524 | 62,909 |
MMBtu
|
$3.16 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $55,798 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.4115: Recover and reuse cooling water | $31,939 | - | - | - | $31,939 | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $17,734 | $5,100 |
$17,734
343,494
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $705 | $1,087 |
$705
13,775
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,750 | $570 |
$1,750
33,998
kWh
|
- | - | |
| 05 | 3.4151: Minimize water usage | $1,269 | - | - |
$500
-
MMBtu
|
$769 | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $1,117 | $220 |
$1,117
21,688
kWh
|
- | - | |
| 07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $698 | $1,195 | - |
$698
-
MMBtu
|
- | |
| 08 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $586 | $40 |
$586
11,430
kWh
|
- | - | |
| TOTAL RECOMMENDED | $55,798 | $8,212 |
$21,892
424,385
kWh
|
$1,198
-
MMBtu
|
$32,708 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs