Assessment Year | 1990 |
---|---|
Principal Product | CONDENSERS |
NAICS |
n/a
|
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 555,563
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $366,858 | 7,801,290 |
kWh
|
$0.047 |
LPG | $109,587 | 23,211 |
MMBtu
|
$4.72 |
Fuel Oil #2 | $1,661 | 473 |
MMBtu
|
$3.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,684 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,099 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2428: Use flue gases in radiant heater for space heating, ovens, etc | $11,076 | $1,932 |
$(-160.0)
(-3,517)
kWh
|
$11,236
-
MMBtu
|
- | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,744 | $900 | - |
$3,244
-
MMBtu
|
$(-500.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,455 | $921 |
$4,455
94,080
kWh
|
- | - | |
04 | 2.7224: Reduce space conditioning during non-working hours | $1,259 | - | - |
$1,259
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $565 | $150 |
$565
12,016
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $361 | $600 |
$361
7,620
kWh
|
- | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $224 | $150 |
$224
4,689
kWh
|
- | - | |
TOTAL RECOMMENDED | $20,684 | $4,653 |
$5,445
114,888
kWh
|
$15,739
-
MMBtu
|
$(-500.0) | ||
TOTAL IMPLEMENTED | $20,099 | $3,903 |
$4,860
102,579
kWh
|
$15,739
-
MMBtu
|
$(-500.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs